Jay and his team have just begun planning phase for their project which has duration of 3 years. Team has gone through project charter and is now developing scope management plan. One of the team members comes to Jay and mentions that project Management plan does not have quality management plan and this is posing challenge. Jay is not sure if quality management plan is a critical input for developing Scope management plan. What may be true from the following in the given scenario?
Project Management plan is not required at this stage
Team member may not be referring to correct version of project management plan
Quality Management plan is independent plan and not part of project management plan
Project management plan will not have all subsidiaries at this stage
My Answer is C but correct is D. Please explain How ?
Scope Management Mockups
Re: Scope Management Mockups
Can you provide the reasoning of why you choose option #c?
Re: Scope Management Mockups
Quality Management Plan is not required at the level of creation of Scope Management Plan. May be high level quality management plan is needed to be required but detail level quality requirement is not necessary as progressive elaboration might required later!
Hopefully it justifies! Manish can explain more ! Option D is a valid choice!
Thank You!
Hopefully it justifies! Manish can explain more ! Option D is a valid choice!
Thank You!
Re: Scope Management Mockups
I would like to know reasoning of Komal for selecting option #C