Scope Management Mockups

Postby komal Wed Aug 16, 2017 1:19 am

What would be termed as conditions or capabilities that are to be met by project or present in the product or service, or result to satisfy an agreement or other formally imposed specification ?

Acceptance criteria

Contractual need

Business case

Requirements

Please explain, my answer is Acceptance Criteria but correct answer showing is Requirements. Could not understand why?
manishpn
Expert
Expert
Posts: 2202
Joined: Sat Jan 04, 2014 3:55 pm

Re: Scope Management Mockups

Postby manishpn Wed Aug 16, 2017 5:39 pm

komal wrote:What would be termed as conditions or capabilities that are to be met by project or present in the product or service, or result to satisfy an agreement or other formally imposed specification ?

Acceptance criteria

Contractual need

Business case

Requirements

Please explain, my answer is Acceptance Criteria but correct answer showing is Requirements. Could not understand why?


This is not a good question as author of this question expect you to memorise the statement about requirements on PMBOK page 112
Acceptance criteria definition is on PMBOK page 123
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/