Scordo - Mock exam 5 question 14

Postby nirajsys@gmail.com Thu Aug 10, 2017 2:00 am

Andy is currently working for ABC contractors as QC manager for a railway track construction project.National railways awarded this cost plus construction contract to ABC contractors a few months ago.As a contractual requirement,ABC has to submit each completed deliverable for client acceptance.Reviewing project data,Andy found out that current submission rejection rate is 22%.He conducts a parent analysis and submit his findings along with construction process improvement recommendations to the project director.

In this scenario,Andy's report is an example of :
A.Work performance data
B.Work performance report
C.Work performance information
D.Work Control Report

My answer to this was B (since he is also recommending after analysing the WP data).I
However Scordo says correct answer is C.

Can group members provide clarity on the same?

Thanks
Niraj.
VCAB
Participant
Participant
Posts: 71
Joined: Wed Dec 21, 2016 4:26 pm

Re: Scordo - Mock exam 5 question 14

Postby VCAB Thu Aug 10, 2017 10:10 am

Andy is currently working for ABC contractors as QC manager for a railway track construction project.National railways awarded this cost plus construction contract to ABC contractors a few months ago.As a contractual requirement,ABC has to submit each completed deliverable for client acceptance.Reviewing project data,Andy found out that current submission rejection rate is 22%.He conducts a parent analysis and submit his findings along with construction process improvement recommendations to the project director.

In this scenario,Andy's report is an example of :
A.Work performance data--- Wrong Answer bc this is raw unprocessed data ie not analyzed
B.Work performance report--- compilation of all analysis done in the monitoring and controlling process group and it is out of the Monitor and Control Project Work
C.Work performance information-- Correct answer, work performance data is analyzed and processed comparing to baselines and project mgt plan
D.Work Control Report--- I don't think this is a real project mgt term