Analogous Estimate

Postby nazrulq Sat Jul 29, 2017 8:10 pm

This is to let you know and confirm the right choice. That topic has been discussed earlier.Just to clarify from Manish or Saket! :D

Here is the question:

Question :Which one of the following would be best described as Analogous Estimates :

a. Pert Estimate.

b. Three Point Estimate with Simple Average

c. Analogous Estimate.

d. Analogous and Parametric Estimate.

Answer : Would be only option C or C & D both.

Thank You!
manishpn
Expert
Expert
Posts: 2203
Joined: Sat Jan 04, 2014 3:55 pm

Re: Analogous Estimate

Postby manishpn Sun Jul 30, 2017 10:27 am

nazrulq wrote:This is to let you know and confirm the right choice. That topic has been discussed earlier.Just to clarify from Manish or Saket! :D

Here is the question:

Question :Which one of the following would be best described as Analogous Estimates :

a. Pert Estimate.

b. Three Point Estimate with Simple Average

c. Analogous Estimate.

d. Analogous and Parametric Estimate.

Answer : Would be only option C or C & D both.

Thank You!


Its a bit difficult to choose.

Option C is ofcourse the best option.
However even in Parametric estimates there can be 2 ways of doing it.
a. Doing parametric estimates after completing certain amount of work in the project,
For e..g. It took two months for the completion of 1 km of road, so in project we estimate how m much it will take to complete 100 kms of road (to keep it simple we are not considering efficiency gain through repetitive tasks)
b. It took one of the previous project 90 months to complete 50 kms of road with X amount of resources , so for my project i can estimate 180 months for 100 Km of road (with similar amount of resources in project)

So option D can also be right
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 237
Joined: Sun Feb 26, 2017 6:06 am

Re: Analogous Estimate

Postby nazrulq Mon Jul 31, 2017 12:32 am

I think exam will not be confusing.

Option 3 is the best choice.

Thank you.