Project Acceptance time

Postby nazrulq Mon Jul 10, 2017 5:18 am

Project sponsor stresses the importance of obtaining stakeholders` formal acceptance of completed deliverables. This should be done:

1 At the end of the project
2 At the end of each project phase
3 After deliverables are completed and ready for review
4 After project milestones are defined

Correct Answer : 3

I think should be option 2

Can somebody explain.
dsharma06
Posts: 11
Joined: Mon Feb 27, 2017 1:02 pm

Re: Project Acceptance time

Postby dsharma06 Mon Jul 10, 2017 7:59 pm

Please read Validate Scope process of PMBOK ( Page Number 133). The correct answer is 3 since we get the deliverables validated/reviewed by the stakeholders/customers.

Thanks
Deepak
nazrulq
Contributor
Contributor
Posts: 239
Joined: Sun Feb 26, 2017 6:06 am

Re: Project Acceptance time

Postby nazrulq Mon Jul 10, 2017 8:07 pm

Thanks not clearly mentioned. Ofcourse when they are ready to deliver.But phase end review also done. Sometimes answers are not cearly defined.