Control Schedule

Postby nazrulq Wed Jul 05, 2017 10:27 pm

Question: Control Schedule is the process of monitoring the status of the project to update project progress and managing changes to the schedule baseline. During this process, you undertake various activities that allow you to identify any changes or potential changes to the project schedule. In this context, which of the following is NOT true about the Control Schedule process?

1 Project manager determines the current status of the project schedule
2 Project manager influences the factors that create schedule changes
3 Project manager takes the anticipated changes through the change control process.
4 Project manager manages the actual schedule changes as they occur

What could be the possible answer!

My Opinion :2
kapil.bhauryal
Beginner
Beginner
Posts: 38
Joined: Fri Apr 07, 2017 3:47 am

Re: Control Schedule

Postby kapil.bhauryal Thu Jul 06, 2017 2:50 am

I will go with Option 3. Project manager takes the anticipated changes through the change control process.
manishpn
Expert
Expert
Posts: 2125
Joined: Sat Jan 04, 2014 3:55 pm

Re: Control Schedule

Postby manishpn Thu Jul 06, 2017 7:11 pm

kapil.bhauryal wrote:I will go with Option 3. Project manager takes the anticipated changes through the change control process.


I agree with Kapil.

please refer to Pag 186 in PMBOK.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 215
Joined: Sun Feb 26, 2017 6:06 am

Re: Control Schedule

Postby nazrulq Fri Jul 07, 2017 3:50 am

The question is asking NOT true. The project manager takes the anticipated changes through the change control process. I think he is NOT influencing changes! He is just pursuing changes through change control board if they occur!

Please Clarify!
VCAB
Participant
Participant
Posts: 71
Joined: Wed Dec 21, 2016 4:26 pm

Re: Control Schedule

Postby VCAB Fri Jul 07, 2017 12:23 pm

I hope I can help here.... The best answer is 3, why, right?
The questions seeks to answer the option that is not true. Option 3 suggests that the controlling process is proactive " Project manager takes the anticipated changes through the change control process." This function is actually right for the planning process (Plan Schedule Management).