Project Closure

Postby nazrulq Mon Jul 03, 2017 5:16 am

Question :

The scope of the project is very well defined and Project Manager has completed all the work described in the contract to his satisfaction, but he thinks, the buyer is not happy with the work. What should he do?

1 Go through arbitration proceedings to ensure that disputes are resolved
2 Talk with senior management about changing the scope of the project to accommodate requirements that would satisfy the customer
3 Ask the customer for input and get her advice on changes that need to be made
4 Move to contract close-out

Correct Answer: Option 4.

My justification all the work defined in the scope were performed as per PM satisfaction. He might inform the buyer while doing the stage-gate review. At the end of the project, the buyer can not perform this kind of behavior.
Project Manager should follow the procedure closing out the project.

Others opinion would be highly appreciated.
kapil.bhauryal
Beginner
Beginner
Posts: 38
Joined: Fri Apr 07, 2017 3:47 am

Re: Project Closure

Postby kapil.bhauryal Mon Jul 03, 2017 6:02 am

I will go with Option D Move to contract close-out,

As per description "scope of the project is very well defined and Project Manager has completed all the work described in the contract to his satisfaction"
manishpn
Expert
Expert
Posts: 2210
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project Closure

Postby manishpn Mon Jul 03, 2017 11:51 am

I would agree with Kapil.

As far as contract scope is completed and all obligations fulfilled PM should move for contract closure.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist