You are finding it difficult to evaluate the exact cost impact of risks. You should evaluate on a(n):

A. Quantitative basis
B. Numerical basis
C. Qualitative basis
D. Economic basis

I have chosen A, but the answer is C
VCAB
Participant
Participant
Posts: 71
Joined: Wed Dec 21, 2016 4:26 pm

Re: Rita - Risk Quality Question

Postby VCAB Wed May 03, 2017 3:59 pm

the Answer is C, the question suggest that you are finding it difficult to technical quantify the cost impact of risk. Answer is used to provide dollar amount of the risk, which is exactly what the question says is difficult. Therefore you would need to use a more subjective measurement, which is C. I would advise that the 47 process group chart understanding the meaning would help you.

The other two options, if I am not mistaken is used for project selection
manishpn
Expert
Expert
Posts: 2343
Joined: Sat Jan 04, 2014 3:55 pm

Re: Rita - Risk Quality Question

Postby manishpn Wed May 03, 2017 4:52 pm

Wally123 wrote:You are finding it difficult to evaluate the exact cost impact of risks. You should evaluate on a(n):

A. Quantitative basis
B. Numerical basis
C. Qualitative basis
D. Economic basis

I have chosen A, but the answer is C


this question is play of words.
The question mentions that PM is finding it difficult to evaluate exact cost impact (this is usually the case when you do not have enough data to feed in to simulation tools to get the $$ output) and in that case the best option is to subjectively categorize risks through qualitative risk analysis
Br,
Manish P