Hi,
Critical path of the project has 3 activities in sequence . Activity A has optimistic estimate as 8,pessimistic as 16 and most likely as 12.Activity B has optimistic estimate as5,Pessimistic estimates as15 and most likely estimate as 0.Activity C has optimistic estimate as 10,pessismistic estimate as 20 and most likely as 15.What is the confidence that project would finish between 34-40 days?
Total project variance comes out to be 9.8 and square root of variance =2.7.Not sure how to solve further - Can you please assist?
Confidence Level
Re: Confidence Level
formula
Confidence Interval= Project Mean +/- 1SD will give you a range at 68% confidence
Project Mean +/- 2SD will give you a range at 95.5% confidence
Project Mean +/- 3SD will give you a range at 99.97% confidence

Confidence Interval= Project Mean +/- 1SD will give you a range at 68% confidence
Project Mean +/- 2SD will give you a range at 95.5% confidence
Project Mean +/- 3SD will give you a range at 99.97% confidence
Re: Confidence Level
1 sigma =68.26%
2 Sigma =95.46%
3 Sigma =99.73%
6 Sigma = 99.99%
Thanks.
2 Sigma =95.46%
3 Sigma =99.73%
6 Sigma = 99.99%
Thanks.
Re: Confidence Level
Thanks - So answer will be .68? Since SD of the project is 2.7?
a).68
b).997
c).95
d).88
a).68
b).997
c).95
d).88
Re: Confidence Level
vaishnavi wrote:Hi,
Critical path of the project has 3 activities in sequence . Activity A has optimistic estimate as 8,pessimistic as 16 and most likely as 12.Activity B has optimistic estimate as5,Pessimistic estimates as15 and most likely estimate as 0.Activity C has optimistic estimate as 10,pessismistic estimate as 20 and most likely as 15.What is the confidence that project would finish between 34-40 days?
Total project variance comes out to be 9.8 and square root of variance =2.7.Not sure how to solve further - Can you please assist?
Such questions are rare in PMP , do not spend too much time on those