discuss-agile-Meetup

Cost Vs Time

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
rajatahaali
Beginner
Beginner
Posts: 23
Joined: Thu Mar 30, 2017 9:47 am

Cost Vs Time

Postby rajatahaali Sun Apr 23, 2017 8:00 am

While going through Schedule Management Knowledge area i observed that Estimate activity cost in an input to Estimate activity resources. Does this imply that budget is made before Schedule management. If that is true than how can one finalize budget without knowing about schedule and estimated durations some activities might take.Or may be they both are made parallel to each other?
rajatahaali
Beginner
Beginner
Posts: 23
Joined: Thu Mar 30, 2017 9:47 am

Re: Cost Vs Time

Postby rajatahaali Sun Apr 23, 2017 8:02 am

Also interestingly Project schedule is an input to Estimate cost. What to do first. Determine Schedule or Estimate Cost?
manishpn
Expert
Expert
Posts: 1923
Joined: Sat Jan 04, 2014 3:55 pm

Re: Cost Vs Time

Postby manishpn Sun Apr 23, 2017 5:47 pm

rajatahaali wrote:While going through Schedule Management Knowledge area i observed that Estimate activity cost in an input to Estimate activity resources. Does this imply that budget is made before Schedule management.
No its a iterative process, after initial few passes if the cost budget is excedding threshold than PM has to revisit the resources needed in project, maybe find cheaper resources.
If that is true than how can one finalize budget without knowing about schedule and estimated durations some activities might take.Or may be they both are made parallel to each other?
We cannot baseline budget without schedule but its iterative process so it takes few iterations before we baseline, in smaller projects maybe we execute them in parallel ,
thats possible

Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
manishpn
Expert
Expert
Posts: 1923
Joined: Sat Jan 04, 2014 3:55 pm

Re: Cost Vs Time

Postby manishpn Sun Apr 23, 2017 5:48 pm

rajatahaali wrote:Also interestingly Project schedule is an input to Estimate cost. What to do first. Determine Schedule or Estimate Cost?


Same response as earlier, its iterative process, however before we baseline budget schedule needs to be in place.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: No registered users and 3 guests