Based on attached question what mean by compress schedule..
Attachments
schedule Question.jpg
schedule Question.jpg (91.99 KiB) Viewed 874 times
manishpn
Expert
Expert
Posts: 2574
Joined: Sat Jan 04, 2014 3:55 pm

Re: Time Management question

Postby manishpn Thu Apr 06, 2017 4:43 pm

we are in develop project schedule process.
Once activity duration estimated are received we need to find ways to optimize the shcedule, using several resource optimization, schedule compression techniques etc before we derive schedule baseline