Work breakdown structure

Postby gagan1986 Thu Mar 16, 2017 12:09 am

Q. A new project manager is being mentored by a more experienced PMP-certified project manager. the new project manager is having difficulty finding enough time to manage the project because the project scope is being progressively elaborated. The PMP-certified project manger advises that the basic tools for project management, such as a work breakdown structure, can be used during project executing to assist the project manager. For which of the following can a work breakdown structure is used?

A. Communicating with the customer.
B. Showing calendar dates for each work packages.
C. Showing the functional manager for each team member.
D. Showing the business need for the project.

Pls clarify this...
manishpn
Expert
Expert
Posts: 2001
Joined: Sat Jan 04, 2014 3:55 pm

Re: Work breakdown structure

Postby manishpn Thu Mar 16, 2017 7:29 pm

As I always recommend, do not look for ready answer,
try to answer by yourself based on your reasoning and then we can debate.

this is a very simple question.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
sreevatsa
Posts: 1
Joined: Tue Feb 28, 2017 6:50 am

Re: Work breakdown structure

Postby sreevatsa Fri Mar 17, 2017 6:05 am

answer is B
sm365
Beginner
Beginner
Posts: 24
Joined: Sat Mar 11, 2017 2:24 pm
Location: Saudi Arabia

Re: Work breakdown structure

Postby sm365 Sat Mar 18, 2017 6:42 am

A - to communicate with customer
VCAB
Participant
Participant
Posts: 66
Joined: Wed Dec 21, 2016 4:26 pm

Re: Work breakdown structure

Postby VCAB Mon Mar 20, 2017 3:18 am

A. Communicating with the customer.
B. Showing calendar dates for each work packages.
C. Showing the functional manager for each team member.
D. Showing the business need for the project.

I used the process of elimination for solve this
C is wrong because it refers to the Human Resource knowledge area and planning phase
D is eliminate because it is initiation phase and Create Project Charter

I later eliminated B, while the WBS package have some information, such as duration and cost, it does not dates.

So, A