Work breakdown structure

Postby gagan1986 Wed Mar 15, 2017 11:59 pm

Q. The work breakdown structure can BEST be thought of as an effective aid for ___________
A. Team
B. Project manager
C. Customer
D. Stakeholder.

Rita answer: Stakeholder
In my opinion, It should be team. Because team has evolvement for WBS. However we don't want to show all of our WBS contents to Stakeholder. It may be risky for project.

Can someone put light on this question. Your support will be much appreciated.
Thnx
manishpn
Expert
Expert
Posts: 2203
Joined: Sat Jan 04, 2014 3:55 pm

Re: Work breakdown structure

Postby manishpn Thu Mar 16, 2017 7:21 pm

This is not a good quality question, Its Aid for team and team and also project stakeholder
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
VCAB
Participant
Participant
Posts: 71
Joined: Wed Dec 21, 2016 4:26 pm

Re: Work breakdown structure

Postby VCAB Mon Mar 20, 2017 3:24 am

I guess the Rita is saying D, right....I guess bc project team is a subset of the universal stakeholder set---in other words, team is stakeholder