Hello,
In project, I knew that the subcontractor/supplier will not comply and delay , what should I do as PM ?
Thanks,
sm365
Beginner
Beginner
Posts: 24
Joined: Sat Mar 11, 2017 2:24 pm
Location: Saudi Arabia

Re: Subcontractor delay

Postby sm365 Tue Mar 14, 2017 9:28 am

Do as per the contract, the provisions for terminations, claims, and contract changes will be specified in your contract.

If you have transferred this contract to a supplier as part of risk transfer, then you have to assess the risk again.

Communicate delays to stakeholders, update issue log.

Also, depends on type of contract.