EVM Hangout Q8

Postby kshitij_y Fri Dec 20, 2013 1:08 pm

Bill is the project manager of a software project that is originally estimated to
complete in 12 months. 2 months into the project, it is discovered that the original
estimating assumptions were fundamentally flawed. The Estimate at Completion
(EAC) in such a project will be:
A. EAC = AC + Bottom-up ETC
B. EAC = BAC/CPI
C. EAC = AC + [BAC - EV]/CPI
D. EAC = AC + BAC - EV