EVM Hangout Q6

Postby indusharma Thu Dec 19, 2013 9:01 am

Rick is a project manager and he is halfway through his project. While making his monthly project performance reports, he observed that cost and schedule variances are very high in the project, since these things are beyond the control he purposed new cost baselines for the project. Management approved the budget of 100,000 for remaining work . Team has already burned through $80,000 till now. What is the estimated cost at completion?

A)$20,000
B)$100,000
C)$180,000
D)$80,000
Indu Sharma
PMP Trainer
iZenbridge Consultancy Pvt Ltd
kshitij_y
PMP
Posts: 229
Joined: Wed Dec 11, 2013 9:39 am

Re: EVM Hangout Q6

Postby kshitij_y Thu Dec 19, 2013 6:19 pm

Ans: C)$180,000