Postby EsakkiMuthu Sat Mar 12, 2016 4:21 am

You are carrying out a project for an external customer. Most of the project's scope of work has been outsourced and distributed among many sub-contractors. What would be the role of the Direct and Manage Project Work process in this scenario?

A-Inspect and verify the adequacy of the seller's product
B-Authorize the seller's work at the appropriate time
C-Assure that the changes are properly approved and communicated
D-The Direct and Manage Project Work process will become redundant in this case
Regards
Esakki
PMI-ACP, PMP
sunildubai15
Contributor
Contributor
Posts: 229
Joined: Sun Nov 29, 2015 5:29 am

Re: another Good question.. Can you guess the answer?

Postby sunildubai15 Thu Mar 17, 2016 12:16 pm

Option B
EsakkiMuthu
Contributor
Contributor
Posts: 191
Joined: Tue Oct 06, 2015 6:11 pm

Re: another Good question.. Can you guess the answer?

Postby EsakkiMuthu Thu Mar 17, 2016 12:22 pm

Yep you are correct
Regards
Esakki
PMI-ACP, PMP
rameshsa@yahoo.com
Contributor
Contributor
Posts: 240
Joined: Thu Aug 20, 2015 5:18 am

Re: another Good question.. Can you guess the answer?

Postby rameshsa@yahoo.com Thu Mar 17, 2016 2:22 pm

Sunil good to see u back
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: another Good question.. Can you guess the answer?

Postby ujjal_show Mon Mar 21, 2016 9:02 pm

This is not a good question.
Because authorizing seller work should be done by work authorization system which is a part of eef.
If PM or PM team are doing that work then why even bother about PM plan -this is reactive and not proactive
EsakkiMuthu
Contributor
Contributor
Posts: 191
Joined: Tue Oct 06, 2015 6:11 pm

Re: another Good question.. Can you guess the answer?

Postby EsakkiMuthu Wed Mar 23, 2016 1:23 am

ujjal_show wrote:This is not a good question.
Because authorizing seller work should be done by work authorization system which is a part of eef.
If PM or PM team are doing that work then why even bother about PM plan -this is reactive and not proactive


In the work authorization system, PM defining how the work will be authorized and also defining the process and procedure.

Since it is distributed among many sub-contractors, PM should have more control, so he is authorizing the work by following the work authorization system. So i dont see any point here as reactive.