why-use-bac/cpi

Postby ATUL1405 Sun Sep 27, 2015 4:38 am

What would be the to-complete performance index of your project based on EAC, given that actual cost of your project is $200,000, cost variance is $20,000 and the initial cost baseline of your project is $300,000?

a.1.2

b.1.1

c.1

d.1.3

why.used.bac/cpi
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: why-use-bac/cpi

Postby ujjal_show Sun Sep 27, 2015 6:15 am

May I know the given explanation. may be asking for new baseline.
santanuded
Beginner
Beginner
Posts: 37
Joined: Fri Aug 21, 2015 7:08 am

Re: why-use-bac/cpi

Postby santanuded Sun Sep 27, 2015 7:39 am

The Questions asks for the TCPI based on EAC.
and the formula is:

TCIP = (BAC-EV)/(EAC-AC)

Now lets see what we have got,

AC=$200,000
CV=$20,000
Initial Cost Baseline = BAC = $300,000

Now,
EV = CV + AC
= $220,000

CPI = EV/AC = 220000/200000 = 1.1


EAC = BAC/CPI = 300000/1.1 = 272727.27

TCIP = (300000 - 220000)/(272727.27 - 200000) =1.1


The formula for EAC is taken as BAC/CPi because the variance is expected to happen at the same rate .. (No data to think other wise)
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: why-use-bac/cpi

Postby manishpn Sun Sep 27, 2015 3:01 pm

Good one Shantanu
Given the information revised EAC is BAC/CPI
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
vivek3377
Super Member
Super Member
Posts: 391
Joined: Thu Sep 10, 2015 2:32 am

Re: why-use-bac/cpi

Postby vivek3377 Sun Sep 27, 2015 4:54 pm

There is a good explaination given by Saket in this video about Earned Value Management -https://www.youtube.com/watch?v=pC1-TwwKkq8
ATUL1405
Participant
Participant
Posts: 52
Joined: Fri Sep 04, 2015 5:17 pm

Re:Questions PMP doubts

Postby ATUL1405 Sun Sep 27, 2015 5:30 pm

thanks . ..

one more question :
Diana is leading a project which has 12 team members. Stacy is leading another project which is been executed from 3 different locations and has 6 team members each. Both these projects are part of a program managed by Sofia. Sofia decides to move two of Diana’s team members into Stacy’s project and reduce Stacy’s team by half. How many communications channel has Dianna reducing in total in her program?

252

234

204

212

its confusing not clear ..i have answer if anyone wants can sahre to explain it .
ATUL1405
Participant
Participant
Posts: 52
Joined: Fri Sep 04, 2015 5:17 pm

Re: why-use-bac/cpi

Postby ATUL1405 Sun Sep 27, 2015 5:33 pm

my exam is on 28th oct and getting anxious ,,going thru saket's registered videos and will go thru rita once . practising online questions of izen.
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: why-use-bac/cpi

Postby manishpn Sun Sep 27, 2015 5:48 pm

Hi Atul, I think the confusing part is 'Sofia decides to move two of Diana’s team members into Stacy’s project and reduce Stacy’s team by half'

It should be 'Sofia decides to reduce stacy team by half and then move two of Diana’s team members into Stacy’s project'

We will rectify it.
Hopefully now the explanation on izenbridge test makes sense to you if not let me know

Steps you should consider is
#1 - Calculate total comm channels in program
#2 - Calculate total comm channels in program after the reduction
#3 calculate difference (reduction in communication channel)

With regards to your exams, let us know your score in Mocks and hope you are focusing on your weak areas
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
thiru26@gmail.com
Contributor
Contributor
Posts: 242
Joined: Sun Sep 13, 2015 10:57 pm

Re: Re:Questions PMP doubts

Postby thiru26@gmail.com Mon Sep 28, 2015 2:00 am

ATUL1405 wrote:thanks . ..

one more question :
Diana is leading a project which has 12 team members. Stacy is leading another project which is been executed from 3 different locations and has 6 team members each. Both these projects are part of a program managed by Sofia. Sofia decides to move two of Diana’s team members into Stacy’s project and reduce Stacy’s team by half. How many communications channel has Dianna reducing in total in her program?

252

234

204

212

its confusing not clear ..i have answer if anyone wants can sahre to explain it .


Here is my math, Please share the answer.
Experts - Correct me if my understanding is wrong

Step 1 - Calculate total Communication Channels in the program - Before Reduction
1 (Program manager) + Total Diana project count 13 (12+ Diana) + Total Stacy Project Count 19 (3 * 6 +1) = 33
Formula = n(n-1)/2 = 33 *32 /2 = 528

Step 2 - Calculate total Communication Channels in the program - After reduction
1 (Program manager) + Total Diana project count 11 ( 12 -2 + Diana, out of 12, 2 of them moved to Stacy) + Total Stacy Project Count 12 (out of 18, reduced to 9 + 2 came from Diana +1 - Stacy itself) = 1 + 11 + 12 = 24 = 276

Step 3 - Subtract Step 1 total - Step 2 total
528 - 276 = 252
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: why-use-bac/cpi

Postby manishpn Mon Sep 28, 2015 7:10 am

Hi thiru your understanding and math is right
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
thiru26@gmail.com
Contributor
Contributor
Posts: 242
Joined: Sun Sep 13, 2015 10:57 pm

Re: why-use-bac/cpi

Postby thiru26@gmail.com Mon Sep 28, 2015 5:36 pm

:roll:
manishpn wrote:Hi thiru your understanding and math is right


Manish,

Thank you.
vivek3377
Super Member
Super Member
Posts: 391
Joined: Thu Sep 10, 2015 2:32 am

Re: why-use-bac/cpi

Postby vivek3377 Tue Sep 29, 2015 12:09 am

Hi Thiru,
Is this question from Scordo's practice exercise? The verbiage of the questions looks familiar! :)
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: why-use-bac/cpi

Postby manishpn Fri Nov 20, 2015 8:00 pm

it was designed by me :)
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
rameshsa@yahoo.com
Contributor
Contributor
Posts: 240
Joined: Thu Aug 20, 2015 5:18 am

Re: why-use-bac/cpi

Postby rameshsa@yahoo.com Fri Dec 25, 2015 9:16 am

How many communications channel has Dianna reducing in total in her program?
Should this not be Sofia (Prg manager).

Then step 2 - when moving 2 team members form diana team to stacy team ...
18+2 = 20 then divide by 2 = 10 + Sofia = 11
11+11+1 = 23 in total...

correct me if i am wrong..
rameshsa@yahoo.com
Contributor
Contributor
Posts: 240
Joined: Thu Aug 20, 2015 5:18 am

Re: why-use-bac/cpi

Postby rameshsa@yahoo.com Fri Dec 25, 2015 6:35 pm

pls help
BhanotN
Posts: 6
Joined: Tue Aug 07, 2018 4:37 pm

Re: why-use-bac/cpi

Postby BhanotN Thu Aug 09, 2018 6:09 pm

Thanks Manish and Atul

It is now clear !!