duration uncertainty

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
wahiba
Participant
Participant
Posts: 60
Joined: Tue Jan 28, 2014 1:59 pm

duration uncertainty

Postby wahiba Fri Mar 07, 2014 6:22 pm

Oliver F. Lehmann 175 free test

question 94 says:

Together with your team, you applied 3 points estimation on a critical path which consists of two activities.

The following duration uncertainties are all calculated assuming a +- 3 Sigma confidence interval.

The duration uncertainty_ define d as pessimistic minus optimistic estimate_ of the first activity is 18 days; tge second has an uncertainty of 24 days.

Applying the pert formula for paths, what is the duration of tge entire path?
User avatar
saket
Site Admin
Site Admin
Posts: 3113
Joined: Sat Dec 07, 2013 10:37 pm

Re: duration uncertainty

Postby saket Sat Mar 08, 2014 1:51 pm

Be careful with this question set the real exam is not as hard as this...

1. In order to solve this question you need to remember that formula for standard deviation (sigma ) is (Pessimistic - Optimistic )/ 6

2. When you have info that this is done at sigma level or % confidence level use sigma value to calculate the pessimistic and optimistic duration.

3. When you have multiple activities in your critical path and you need to calculate the sigma at overall level (sum level) do not sum the sigma of all activities rather sum the variance (sigma *sigma) of all activities and then calculate the sigma at path level.

4. Since only two activities and no info about the sequence is given you need to assume they are serial

5. Duration Uncertainty is defined here as Pessimistic - Optimistic which is equal to 6*sigma , so you need to calculate the sigma of these two activities combined and multiply it by 6

Question94-Sigma.gif
Question94-Sigma.gif (21.53 KiB) Viewed 4722 times


Hope this explanation will help. :)
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: duration uncertainty

Postby namita Sat Mar 08, 2014 2:29 pm

Nice Explanation Saket
wahiba
Participant
Participant
Posts: 60
Joined: Tue Jan 28, 2014 1:59 pm

Re: duration uncertainty

Postby wahiba Sat Mar 08, 2014 2:39 pm

But what is the variance (sigma *sigma)
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: duration uncertainty

Postby namita Sat Mar 08, 2014 2:43 pm

Variance is always Sigma Square
User avatar
saket
Site Admin
Site Admin
Posts: 3113
Joined: Sat Dec 07, 2013 10:37 pm

Re: duration uncertainty

Postby saket Sat Mar 08, 2014 2:44 pm

Variance is Square of Sigma = ((P-0)/6)^2
Variance = (Sigma)^2
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
wahiba
Participant
Participant
Posts: 60
Joined: Tue Jan 28, 2014 1:59 pm

Re: duration uncertainty

Postby wahiba Sat Mar 08, 2014 2:50 pm

Ok I got it :shock: :D
wahiba
Participant
Participant
Posts: 60
Joined: Tue Jan 28, 2014 1:59 pm

Re: duration uncertainty

Postby wahiba Sat Mar 08, 2014 2:51 pm

Always or when there is more than one activity?
User avatar
saket
Site Admin
Site Admin
Posts: 3113
Joined: Sat Dec 07, 2013 10:37 pm

Re: duration uncertainty

Postby saket Sat Mar 08, 2014 3:27 pm

It is always, when we have more than one activity and we want to know variance at path level... we need to sum the variance and in order to calculate the sigma we need to take square root of variance.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: Bing [Bot] and 7 guests