Network Diagram

Postby sachin07 Fri Aug 28, 2015 7:48 am

Hi All,

I am bit confused about attached network diagram details as one activity estimate is provided two time. Can someone suggest me on it, please ?

Regards
Sachin
Attachments
T4a.jpg
T4a.jpg (16.29 KiB) Viewed 1290 times
bhuvanpanwar1983
Contributor
Contributor
Posts: 160
Joined: Tue Jun 30, 2015 2:24 pm

Re: Network Diagram

Postby bhuvanpanwar1983 Fri Aug 28, 2015 9:42 am

I haven't seen this before but by looking at this can be make out that there will be more than 1 critical path - so not good for the project.
There are 3 task as start activity with different duration - and overlapping each other and same goes for end activity as well.
coolpmp69
Contributor
Contributor
Posts: 282
Joined: Mon Nov 17, 2014 8:55 pm

Re: Network Diagram

Postby coolpmp69 Fri Aug 28, 2015 1:23 pm

For this question, you need to first draw the network diagram and then calculate critical path. As we don't know the type of dependencies(SS,SF, FS, FF), don't get into the details and also this info is not required to solve this question.

For some reason, I'm unable to attach the critical path image, so here is the calculation

Length of different paths
start->1->2->end = 10 months
start->3->5->end = 11 months
start->4->5->end = 12 months

so critical path = start->4->5->end = 12 months