Which option is NOT representative of the inputs, tools and techniques, and outputs
of the Direct and Manage Project Work process?
A. PMIS, Project Management Plan, and Deliverables
B. Deliverables, Approved Change Requests, and Project Management
Information System
C. Approved Change Requests, Validated Changes, and PMIS
D. Approved Change Requests, Project Management Plan, and Work
Performance Data

I picked up answer being option D , as all 3 are either input or out but not TT, as I understood which option above doesn't not contain all 3 ITTO.
Please clarify
AM1969
Contributor
Contributor
Posts: 194
Joined: Fri Dec 05, 2014 7:05 pm

Re: ITTO Question

Postby AM1969 Tue Aug 25, 2015 4:54 pm

Option C is the answer....validated changes is input to M&C project work
coolpmp69
Contributor
Contributor
Posts: 282
Joined: Mon Nov 17, 2014 8:55 pm

Re: ITTO Question

Postby coolpmp69 Tue Aug 25, 2015 5:36 pm

Agree with AM1969, answer is option C