change request

Postby AM1969 Mon Mar 23, 2015 8:41 pm

The marketing head of your company raised an issue that he is not being kept in loop about the change in release date of project, you looked at Project Communication Management Plan and found that he is not included in the list of stakeholders who gets an update related to project schedule variances. You feel that marketing head should be included in schedule related communications, what should you do next?

Include Marketing head in all future schedule related communications

Update the Communication Management Plan

Raise a Change Request

Tell marketing head that he can anytime call you and get the desired information

......................
In some answers option is to raise a change request and somewhere answer is to update communication mgt plan.
Please clarify
manishpn
Expert
Expert
Posts: 2451
Joined: Sat Jan 04, 2014 3:55 pm

Re: change request

Postby manishpn Mon Mar 23, 2015 9:38 pm

Usually updating project communication plan for addition of key stakeholders to receive project status update (Unless its sensitive and restricted information) does not necessitate a formal Change request process.

Communication management plan is update with revised version

you can refer to PMBOK page 307 and 308.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
pank_pmp
Super Member
Super Member
Posts: 490
Joined: Tue Aug 05, 2014 11:04 am

Re: change request

Postby pank_pmp Tue Mar 24, 2015 4:11 am

Depending upon the stakeholder type and information being sensitive or not or right information being shared with right stakeholder, PM can decide on updating communication plan and or for that matter stakeholder management plan. In this scenario I do not see any issues in updating directly communication management plan instead of raising a change request.
AM1969
Contributor
Contributor
Posts: 194
Joined: Fri Dec 05, 2014 7:05 pm

Re: change request

Postby AM1969 Tue Mar 24, 2015 1:24 pm

answer here is ----C raise a change request.
dipti5ece
Contributor
Contributor
Posts: 134
Joined: Tue Sep 09, 2014 8:31 am

Re: change request

Postby dipti5ece Tue Mar 24, 2015 1:45 pm

this would not require a CR ..also this is not affecting any other project constraints.

So I think we can update the comm plan.
pank_pmp
Super Member
Super Member
Posts: 490
Joined: Tue Aug 05, 2014 11:04 am

Re: change request

Postby pank_pmp Tue Mar 24, 2015 2:01 pm

answer here is ----C raise a change request.


Which we do not agree with. What is the source of question?
pank_pmp
Super Member
Super Member
Posts: 490
Joined: Tue Aug 05, 2014 11:04 am

Re: change request

Postby pank_pmp Tue Mar 24, 2015 2:18 pm

answer here is ----C raise a change request.


Which we do not agree with. What is the source of question?
coolpmp69
Contributor
Contributor
Posts: 282
Joined: Mon Nov 17, 2014 8:55 pm

Re: change request

Postby coolpmp69 Tue Mar 24, 2015 3:34 pm

I think PM can directly go and update the communication management plan and do not need a CR for this.

In PMBOK 308, it is mentioned that control communication can result in communication plan update.

"Control Communications process may trigger updates to the communications management plan as well as
other components of the project management plan (e.g. stakeholders and human resource management plans)."
User avatar
saket
Site Admin
Site Admin
Posts: 3127
Joined: Sat Dec 07, 2013 10:37 pm

Re: change request

Postby saket Fri Mar 27, 2015 3:27 pm

May want to look at this thread as well : viewtopic.php?f=3&t=1954&p=7268
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
AM1969
Contributor
Contributor
Posts: 194
Joined: Fri Dec 05, 2014 7:05 pm

Re: change request

Postby AM1969 Fri Mar 27, 2015 3:54 pm

source of question is quampus assignment which gives answer C change request.
User avatar
saket
Site Admin
Site Admin
Posts: 3127
Joined: Sat Dec 07, 2013 10:37 pm

Re: change request

Postby saket Fri Mar 27, 2015 4:08 pm

I hope the thread i shared answers it, and we do not have any rule which says raise the change request or not raise it. PMBOK use may for both the case, and what you do, you do as per your change management plan, in exam look for options and pick the one which is safest.

Please discuss quampus questions in exclusive area it helps us in linking with other threads.

sharing the comment from thread here again
Many time this becomes confusing related to some of the project documents and project management plan

1. Its not necessary to follow change request for all project plan and project document update, and that is the reason many processes gives output of update project document and update project management plan.

2. We need to define in Change Management Plan about which all documents / plans gets updated only via formal change management process.

3. In general if something has to do with time,cost and scope it goes via formal change management process.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: No registered users and 13 guests