WPI vs WPD

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
coolpmp69
Contributor
Contributor
Posts: 282
Joined: Mon Nov 17, 2014 8:55 pm

WPI vs WPD

Postby coolpmp69 Mon Mar 09, 2015 4:55 pm

A project team has recently computed the project's current schedule and cost performance indices. They have also calculated the new estimate to complete and the TCPI based on the new estimate at completion. The project key stakeholders are not fully aware of the earned value management process. These measures in this case are an example of?
a Work performance data
b Lessons learned
c Work performance information
d Learning curve for the stakeholders
Amit Singh
Beginner
Beginner
Posts: 45
Joined: Fri Dec 05, 2014 4:37 am

Re: WPI vs WPD

Postby Amit Singh Tue Mar 10, 2015 3:57 am

Hi,

Its Work Performance Information.

Work Performance Data are the raw observation and measurements ( e.g start and finish dates, actual cost,actual duration etc.)
Work Performance information are data collected from various controlling processes ( e.g status of deliverable, forecasted estimates to complete )
Regards,

Amit.
nandita
Beginner
Beginner
Posts: 22
Joined: Fri Mar 21, 2014 9:06 am

Re: WPI vs WPD

Postby nandita Tue Mar 17, 2015 12:39 pm

Hi ,

Yes its Work performance data .

Work performance data- Row data -
further analysis of Work performance data (Row data) will give Work performance information-
More further analysis will be Work performance report (For senior management or presentation ).

Kind Regards:
Nandita Nandan.
coolpmp69
Contributor
Contributor
Posts: 282
Joined: Mon Nov 17, 2014 8:55 pm

Re: WPI vs WPD

Postby coolpmp69 Tue Mar 17, 2015 1:34 pm

the correct answer is work performance data
dipti5ece
Contributor
Contributor
Posts: 134
Joined: Tue Sep 09, 2014 8:31 am

Re: WPI vs WPD

Postby dipti5ece Thu Mar 19, 2015 9:22 am

why cant it be WPI?
Amit Singh
Beginner
Beginner
Posts: 45
Joined: Fri Dec 05, 2014 4:37 am

Re: WPI vs WPD

Postby Amit Singh Thu Mar 19, 2015 10:33 am

Hi,

As per the PMBOK Guide, the work performance information is “the performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas; e.g. status of deliverable, and forecasted estimates to complete, etc.”,Here, you will analyze the work performance data. You will compare the planned performance with actual performance.

As the question says " They have also calculated the new estimate to complete and the TCPI based on the new estimate at completion" & "These measures in this case are an example of?" , TCPI is T&T of Control cost and its one of the output is WPI.

Not sure how can it be WPD & not WPI.

As per the PMBOK Guide, the work performance data is “the raw observations and measurements identified during activities performed to carry out the project work; e.g. actual cost, actual duration, and percent of work physically completed.”

Might be the possibility where i am unable to relate the actual question asked / misunderstood the question.
Regards,

Amit.
coolpmp69
Contributor
Contributor
Posts: 282
Joined: Mon Nov 17, 2014 8:55 pm

Re: WPI vs WPD

Postby coolpmp69 Thu Mar 19, 2015 1:27 pm

@ Amit: I agree with your point. The answer should be WPI. But Scordo cannot be wrong :(
Still does not make sense.

Here is the explanation :

Explanation/Answer : A - The scenario gives a situation where the project team has calculated some measures that need to be transformed into a format that the project stakeholders might understand. These measures are work performance data for this project. Work performance information is always in a format that can be easily understood by the project stakeholders. This is clearly neither an example of lessons learned nor is it an example of a learning curve for the stakeholders. [PMBOK 5th edition, Page 411]
manishpn
Expert
Expert
Posts: 2403
Joined: Sat Jan 04, 2014 3:55 pm

Re: WPI vs WPD

Postby manishpn Thu Dec 07, 2017 3:24 pm

its WPI, i do not agree with explanation provided by scordo
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: Bing [Bot], Google [Bot] and 15 guests