Control Quality is the process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes. To evaluate control quality output data, the project team must ideally have a working knowledge of:
1. Prevention and inspection
2. Sampling and probability
3. Special causes and random causes
4. Tolerances and control limits

Re: Control Quality

Posted: Wed Feb 25, 2015 3:24 am
by pank_pmp
I guess Option 1 seems to be more appropriate!

Re: Control Quality

Posted: Wed Feb 25, 2015 7:33 am
by dipti5ece
2. Sampling and probability ?i guess

Re: Control Quality

Posted: Wed Feb 25, 2015 1:50 pm
by coolpmp69
2. Sampling and probability is correct answer but why not option 1?

Re: Control Quality

Posted: Fri Feb 27, 2015 10:49 pm
by narendraupadhyay
I think prevention should be done before control quality (during quality assurance).
During control quality, in large projects, we may need to do more sampling checks, so team may need to have a working knowledge of statistical control processes (sampling and probability) to evaluate the data of control quality.

Regards,
Narendra

Re: Control Quality

Posted: Sat Feb 28, 2015 5:55 am
by pank_pmp
I think I overlooked the question and Option 2 seems to be correct since it is talking about To evaluate control quality output data.

Option 1 (Prevention and inspection ) and especially inspection is what we do while performing control quality process.

Re: Control Quality

Posted: Sat Feb 28, 2015 3:28 pm
by signor_rk
I think while referring to Page # 250 , 1st sentence of the 2nd Para , PMBOK Guide Fifth Edition , it gives some hints which states that " The project management team may have a working knowledge of statistical control processes to evaluate data contained in the control quality outputs."

Thanks.

Re: Control Quality

Posted: Mon Mar 02, 2015 2:10 pm
by coolpmp69
Based on Ranjit's input, the answer should be prevention and inspection then given in PMBOK.

Saket...need your inputs here.

Re: Control Quality

Posted: Mon Mar 02, 2015 3:04 pm
by signor_rk
No. What it hints is the Statistical Control Processes/Statistical Process Control (SPC), which is a method of quality control that uses statistical methods.
( Reference to http://en.wikipedia.org/wiki/Statistica ... ss_control )

So , the correct Option # 2. Sampling and probability

Thanks

Re: Control Quality

Posted: Tue Mar 03, 2015 1:44 pm
by coolpmp69
Got it..thanks

Re: Control Quality

Posted: Wed Mar 04, 2015 3:27 pm
by saket
The question can be looked as which of the following tools/ techniques used in Perform Quality Assurance.