Confusing QTS 2015

Postby dipti5ece Tue Feb 17, 2015 9:49 am

Two project team members have resigned from your company. However, you are able to negotiate with functional managers in your organization to get two resources quickly as substitutes. From a stakeholder management point of view, this can be referred to as:
1 Pre-assignment
2 Corrective action
3 Approved change request
4 Resolved issue
pank_pmp
Super Member
Super Member
Posts: 490
Joined: Tue Aug 05, 2014 11:04 am

Re: Confusing QTS 2015

Postby pank_pmp Tue Feb 17, 2015 11:28 am

It will be better if you can share your understanding against each point, which will be more helpful in discussion. For me it is more like Option D.

1. Pre-assignment
Replacement is not Pre-assignment!

2. Corrective action
Nothing wrong have done to call it as corrective action.

3. Approved change request
Cannot be option here.

So most likely for me it should be Resolved issue, while looking at the option.
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Confusing QTS 2015

Postby signor_rk Wed Feb 18, 2015 11:17 am

To also agree with Pankaj.

Option # 4 Resolved issue
Regards ,

Ranjit