Change request

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
abhivyaghra
Posts: 6
Joined: Fri Feb 08, 2019 12:56 pm

Change request

Postby abhivyaghra Fri Jul 12, 2019 12:43 pm

Does it required to do analysis before initiate for any change request
manishpn
Expert
Expert
Posts: 2721
Joined: Sat Jan 04, 2014 3:55 pm

Re: Change request

Postby manishpn Wed Jul 17, 2019 3:24 pm

abhivyaghra wrote:Does it required to do analysis before initiate for any change request


Depends on the situation cant give a blanket response , usually an issue is converted to a CR, if there is a change needed to solve the issue.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
abhivyaghra
Posts: 6
Joined: Fri Feb 08, 2019 12:56 pm

Re: Change request

Postby abhivyaghra Wed Jul 17, 2019 4:01 pm

Sir, below question is from izenbridge mock test 1.in given situation I consider to do the analysis before giving change request as my next move but the correct answer is C. Please explain
A project manager (PM) is handing a high value and a high-risk project in a globally recognized MNC. There are few high-value critical parts whose costs are not stable due to market instabilities yet required to be outsourced immediately. After placement of contract, the PM receives intermediate invoices from the vendor as per agreed schedule. Upon reviewing the invoices, PM realizes that the cost escalations are too high and will eventually impact the cost baseline. What should the project manager do next?

Cancel the contract and change the contract type to fixed price with Economic Price Adjustment Type.

Report to the senior management

Raise a change request for approval

Do analysis if cost escalations are valid