Scrum-Master-Forum

Project closure process.

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
akc
Beginner
Beginner
Posts: 34
Joined: Sat Jun 15, 2019 3:09 am

Project closure process.

Postby akc Sat Jun 22, 2019 7:53 am

At the time of project closure team performance review, reward & release is carried out at the which stage? Is it before archival of all the project documents & after ?
manishpn
Expert
Expert
Posts: 2795
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project closure process.

Postby manishpn Sun Jun 23, 2019 10:55 am

akc wrote:At the time of project closure team performance review, reward & release is carried out at the which stage? Is it before archival of all the project documents & after ?


team performance review are not done during project closure only, during project or phase closure the performance assessment are updated to OPA,

The update to OPA has to be done before archival, once archival is done update to documents is difficult
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
akc
Beginner
Beginner
Posts: 34
Joined: Sat Jun 15, 2019 3:09 am

Re: Project closure process.

Postby akc Sun Jun 23, 2019 5:51 pm

Your reply implies that team performance appraisal is carried out before project document archival.
manishpn
Expert
Expert
Posts: 2795
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project closure process.

Postby manishpn Sat Jul 06, 2019 12:58 pm

Yes, if you do that after archive the ream performance appraisal will not be part of the archive files
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: No registered users and 12 guests