In which time mgmt process do we apply lead and lag?

Re: Lead n Lag

Posted: Mon Jan 19, 2015 3:46 am
by Amit Singh
Hi Dipti,

Lead and Lag is applied while Sequence Activities, its T&T of sequence Activities.

Re: Lead n Lag

Posted: Mon Jan 19, 2015 4:14 am
by signor_rk
To be more exact , Leads and Lags are applied in the following processes:

(a) Sequence Activities
(b) Develop Schedule
(c) Control Schedule
(Reference Page # 143 Figure 6-1 PMBOK Guide Fifth Edition)