Schedule baseline

Posted: Wed Jan 07, 2015 7:19 am
by Mohammed
1.Schedule baseline
2.Project schedule
3.Schedule data

What is different ?

Re: Schedule baseline

Posted: Wed Jan 07, 2015 7:53 am
by saket
Lets look at the glossary definition of these three terms

Schedule Data. The collection of information for describing and controlling the schedule.

Project Schedule. An output of a schedule model that presents linked activities with planned dates, durations,
milestones, and resources.

Schedule Baseline. The approved version of a schedule model that can be changed only through formal change
control procedures and is used as a basis for comparison to actual results.


Schedule data is base data like resource , activity , constraints , which results in project schedule, and one of the project schedule version which we pick for reference is baseline schedule, so baseline schedule is also a project schedule but not all project schedule are baselined.

Re: Schedule baseline

Posted: Wed Jan 07, 2015 9:50 am
by Mohammed
Thank you, MR Saket

but Why Project schedule INPUT control schedule ?

Re: Schedule baseline

Posted: Wed Jan 07, 2015 2:59 pm
by signor_rk
Project Schedule is a live document , unlike the Schedule Baseline which can be updated/re-baselined only through formal Change Control procedure.

Re: Schedule baseline

Posted: Wed Jan 07, 2015 4:20 pm
by saket
Because control schedule looks into variance between project schedule (the current schedule which is updated based on reality ) and baseline schedule (included in project management plan ) .