On Manage project Team, Q could be wrongly phrased

Posted: Sat Dec 20, 2014 12:55 pm
by raghu
Source: www.tutorialspoint.com

The process of Manage project team uses which of the following inputs in its execution?

A. Issue Log
B. Resource Calendars
C. Activity Resource Requirements
D. Human Resource Management Plan

Answer:A
Hint: PMBOK 5, Page 257, Sec 9.4


For this question, answer should have been given as Both 'A' and 'D'. Isn't it?

Re: On Manage project Team, Q could be wrongly phrased

Posted: Sat Dec 20, 2014 3:54 pm
by pank_pmp
As per PMBOK both A and D are inputs for Manage Project Team. So I think You should avoid such questions for exam point of view!

Re: On Manage project Team, Q could be wrongly phrased

Posted: Sat Dec 20, 2014 4:43 pm
by signor_rk
Yes , it's better to avoid some questions like this.

Re: On Manage project Team, Q could be wrongly phrased

Posted: Mon Dec 22, 2014 2:15 am
by saket
Yes you are right, not to take any test question or answer as final conclusion, we need to put our PMBOK and project management knowledge in use, since PMI is going to judge us based on that.

Re: On Manage project Team, Q could be wrongly phrased

Posted: Mon Dec 22, 2014 6:08 am
by dipti5ece
According to me both are right answers but then we must be selecting the best one.

Issue log is one of the main inputs in Manage prj team process.

Re: On Manage project Team, Q could be wrongly phrased

Posted: Mon Dec 22, 2014 6:26 am
by pank_pmp
According to me both are right answers but then we must be selecting the best one.

Issue log is one of the main inputs in Manage prj team process.


I disagree with this! PMBOK is bible for exam! Choosing "Best ones" are not direct questions and more of conditional based. For instance, which is the best/immediate OPTION is to do :) . Such questions may have couple of or may be all of the options right but one need to choose the best next approach.

This question directly referring to ITTO of Manage Project Team process.

Re: On Manage project Team, Q could be wrongly phrased

Posted: Wed Dec 24, 2014 8:58 pm
by raghu
Thank you Dipti for bringing a different point.

You may be wrong. But would like to know the view points here and adherence to PMBOK.
Please elaborate bit more on why you think "Issue Log" is the main input for Manage Project team process?