Question related to activity duration

Posted: Mon Dec 08, 2014 11:07 am
by Samhita
Can anyone solve this query?

The activity “Ship Container” in Raj’s network diagram has an early start of day 17, a late start of day 22 and a late finish of day 37. What is the activity duration?
A.) 14 days
B.) 16 days
C.) 33 days
D.) 24days

Re: Question related to activity duration

Posted: Mon Dec 08, 2014 1:43 pm
by Shant
I THINK 16 DAYS..

Re: Question related to activity duration

Posted: Mon Dec 08, 2014 2:41 pm
by signor_rk
You are right Shant. Option # B) 16 days

Justification:

Activity Duration = LF - LS +1 = 37 - 22 + 1 = 16 days.