One more.
Your 3-year project finished 4 months early. What is your final SPI?
[list=]
0.89
1.13
1.04
1
[/list]

I calculated 0.89, but the correct answer is 1 again ... is it that the SPI after completion will always be 1 ... ?
-----------------
Regards, Niraj
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Earned Value - SPI at completion (q2)

Postby signor_rk Mon Dec 01, 2014 6:22 pm

Yes. That is the thumb rule so far to my understanding. Because we will be re-base lining our schedule.