Earned Value - SPI at project completion

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
kniraj
Participant
Participant
Posts: 59
Joined: Sat Oct 11, 2014 4:45 pm

Earned Value - SPI at project completion

Postby kniraj Mon Dec 01, 2014 5:48 pm

You are completing your final project report. You include information on the final variances. If the project was scheduled to take 12 months, and it finished in 14 months, what would your final SPI results be?
[list=]1
1.17
0.86
Not enough information to determine[/list]

The answer is 1, can someone please help and explain this.
-----------------
Regards, Niraj
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Earned Value - SPI at project completion

Postby signor_rk Mon Dec 01, 2014 6:18 pm

When a project is completed , it's SPI =1 and SV = 0
This is the thumb rule !!! :)
Regards ,

Ranjit
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Earned Value - SPI at project completion

Postby saket Tue Dec 02, 2014 11:47 am

SPI is not a measure of how much behind we are from schedule, it is how much % of planned work is completed till this time, so when project finish we end up finishing all the work may be delayed by time but all gets done.

So at the end of project we achieve the complete planned value and that makes EV = PV and SPI =1 , i stressed on this part in my EVM webinar , here are the 3 videos you may like to refer to.

https://www.youtube.com/watch?v=OtAw6FqACzs
https://www.youtube.com/watch?v=EfyxCZv5gQ4
https://www.youtube.com/watch?v=lqvZFKxe3Gk
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
kniraj
Participant
Participant
Posts: 59
Joined: Sat Oct 11, 2014 4:45 pm

Re: Earned Value - SPI at project completion

Postby kniraj Tue Dec 02, 2014 1:09 pm

Ranjit and Saket, Thanks .. will go thru the videos once i reach home :) I plan to give the exam on the 26th Dec so currently giving as many mock exams as possible
-----------------
Regards, Niraj
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Earned Value - SPI at project completion

Postby signor_rk Tue Dec 02, 2014 1:46 pm

You are welcome and wish you good luck for your Exam as well.
Regards ,

Ranjit
dipti5ece
Contributor
Contributor
Posts: 134
Joined: Tue Sep 09, 2014 8:31 am

Re: Earned Value - SPI at project completion

Postby dipti5ece Wed Dec 03, 2014 5:53 am

I found the above 3 webinar vidoes on EVM very useful and to the point.

Thankyou Saket :)