PMP Question

Postby taterarpit Sat Sep 06, 2014 8:11 pm

You have just been authorized to manage a new project for your company. Which of the following BEST
describes your first action?

Create the work breakdown structure
Develop the project management plan
Develop the project charter
Create the preliminary scope statement
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: PMP Question

Postby saket Sun Sep 07, 2014 1:24 am

Looks like PMBOK 4 or older question because now we do not have process called "Create the preliminary scope statement"

Create the work breakdown structure

You can not create it till you have scope
Develop the project management plan

You will start working on it but others are also part of it , not sure develop mean start or finish. because you can not make Project management plan till you make scope etc.
Develop the project charter

Should be given to you as part of authorization
Create the preliminary scope statement

As per old PMBOK this looks the closest.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
taterarpit
Contributor
Contributor
Posts: 111
Joined: Sat Jul 26, 2014 6:42 pm

Re: PMP Question

Postby taterarpit Sun Sep 07, 2014 4:44 pm

Hi Saket,

In current situation i.e PMBOK v5 ...what should be the correct answer according to you...i posted same question on LinkedIn and there also participants are confused in B&D so not sure...what should be the correct answer...
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: PMP Question

Postby saket Sun Sep 07, 2014 4:48 pm

The D looks good.
Create the preliminary scope statement
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: PMP Question

Postby umeshbww Sun Sep 07, 2014 7:30 pm

Arpit - as we discussed Rita's process chart : viewtopic.php?f=3&t=1373 planning is always in set order. :D
If you follow Rita's chart - you would get your answer.

Definitely D option Create the preliminary scope statement

As pointed out by Saket - I followed same strategy.

Project Charter initiate project and authorize PM officially. (already done as per Q).
You can't create PMP or WBS until you have defined scope. (Scope management -> Collect requirement -> Define Scope -> Create WBS)

Project Scope statement, WBS and WBS Dictionary together form Scope baseline which is part of PMP.