Closing Phase Question

Posted: Wed Sep 03, 2014 2:08 pm
by taterarpit
I always stuck while answering question regarding the exact sequence of closing phase ...

Which of the following is the correct order of actions that you take during the closing processes?

A.Get formal acceptance, release the team, write lessons learned, close the contract
B.Write lessons learned, release the team, get formal acceptance, close the contract
C.Get formal acceptance, write lessons learned, hand over deliverable to stakeholder(s), close the contract
D.Get formal acceptance, close the contract, write lessons learned, release the team

Re: Closing Phase Question

Posted: Wed Sep 03, 2014 2:23 pm
by signor_rk
I choose Option # D.Get formal acceptance, close the contract, write lessons learned, release the team

Re: Closing Phase Question

Posted: Wed Sep 03, 2014 3:03 pm
by taterarpit
writing lessons learned is done only by project manager or team....

i am specifically talking about project closure..i mean once customer has accepted deliverable , after that...only project manager would write lessons learned with the help of all the documents prepared during the course of the project or team? Thanks!!

Re: Closing Phase Question

Posted: Fri Feb 03, 2017 12:17 am
by Housam Bassal
Project team cannot be released before complete all the project works, hence a, b are not correct.
Contract cannot be close before complete all project work , hence option D is not correct.

Correct answer is C.