Crashing or Fast tracking

Postby nagarwal Tue Sep 02, 2014 11:31 am

Why can't option C be the answer. Why fast tracking is the answer here and why not crashing?
Attachments
crashing vs fast tracking.png
Crashing vs file crashing
crashing vs fast tracking.png (132.02 KiB) Viewed 637 times
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Crashing or Fast tracking

Postby signor_rk Tue Sep 02, 2014 4:26 pm

Since the Company has already invested a lot , so in order to complete the project on time with the EXISTING RESOURCES , Fast Tracking is the best option in this case.
Regards ,

Ranjit
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Crashing or Fast tracking

Postby namita Wed Sep 03, 2014 4:52 am

Agree with Ranjit

1. Question route towards and indication of money already spent is huge so there won't be much room now
2. Crashing need more resources and question specifically telling about using existing resources