You are a project manager in a telecom project and 10 engineer report to you. Two new members start reporting to you. How many communication channels will be added by including these two new members.

a)21
b)23
c)66
d)78

Calulating the no. of channels is no problem here. Figuring out when to include the project manager in the communication channel is the real worry. Is there any logic to get these kind of questions right. Many a times I assume that we need to additionally count the project manager and get the answer right and many a times it turns out to be incorrect. Any suggestions here?
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Communication Channel

Postby signor_rk Tue Sep 02, 2014 4:16 pm

I think the description of the sentence matters most. In this particular question the PM needs to be considered while counting for the number of team members for communication channels.
Regards ,

Ranjit
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Communication Channel

Postby namita Wed Sep 03, 2014 4:47 am

I will not answer this question until you go through below and if you still have question.. most welcome to discuss :)

Blog: http://www.izenbridge.com/blog/izenbrid ... -channels/
Video: https://www.youtube.com/watch?feature=p ... 0X1DUVUf28
Mohammed
Posts: 19
Joined: Tue Sep 02, 2014 7:55 am

Re: Communication Channel

Postby Mohammed Wed Sep 03, 2014 8:14 am

you must add PM
ALL stakeholder =13 people
Old team (include PM)=11 people
(11*10)/2 = 55
(13*12)/2 = 78

78-55 = 23
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: Communication Channel

Postby umeshbww Wed Sep 03, 2014 5:02 pm

I am not sure why this question is confusing in sense to add PM or not.

Question explicitly mentions 10 engineers report to you :) which suggests PM is not counted.