Question of critical path

Postby nagarwal Mon Sep 01, 2014 3:28 pm

Activity A has a duration of 6 days and has 4 days of free float. The ES of successor activity B is day 18. If activity A is delayed by 7 days, what is the adjusted early start of activity B? More than knowing the right answer,it would be great to know the way to calculate it?
Day 11
Day 21
Day 31
Day 25
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Question of critical path

Postby saket Mon Sep 01, 2014 4:27 pm

Free Float. The amount of time that a schedule activity can be delayed without delaying the early start date of any
successor or violating a schedule constraint.


We also had blog on this : http://www.izenbridge.com/blog/what-is- ... ree-float/
Attachments
FreeFloat.jpg
FreeFloat.jpg (40.78 KiB) Viewed 1142 times
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Question of critical path

Postby signor_rk Mon Sep 01, 2014 5:11 pm

Can someone please review my calculation as in the attached sketch :
Attachments
net-99.JPG
net-99.JPG (192.27 KiB) Viewed 1119 times
Regards ,

Ranjit
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Question of critical path

Postby saket Tue Sep 02, 2014 12:42 am

It looks perfect signor_rk
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
nagarwal
Participant
Participant
Posts: 60
Joined: Sun Jun 22, 2014 8:34 am

Re: Question of critical path

Postby nagarwal Tue Sep 02, 2014 2:39 am

Thanks guys! That's really of great help. Appreciate it!
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Question of critical path

Postby signor_rk Tue Sep 02, 2014 4:08 am

Thanks Saket for the confirmation. Thanks for such a good question too @nagarwal ... :)
Regards ,

Ranjit