Question on change?

Posted: Fri Aug 29, 2014 11:24 am
by nagarwal
The deliverables as well as the schedule baselines of your project have been changed three times. Which of the following is MOST LIKELY the cause of the changes?
 
1. The lack of clear instructions from project sponsor.
 
2. Incomplete project management plans.

3. The lack of a signed-off project charter.

4. Incomplete project scope management plans

Re: Question on change?

Posted: Fri Aug 29, 2014 6:42 pm
by umeshbww
I will choose option 2. Incomplete project management plans

Project Charter is high level documents and don't have detailed deliverables or schedule baseline.

Although incomplete scope management plan can also have ripple effect in changing deliverables and schedule baselines.

Re: Question on change?

Posted: Sat Aug 30, 2014 8:03 am
by signor_rk
The best possible Option is the Option # 1 1. The lack of clear instructions from project sponsor. The other options follow thereafter.
 

Re: Question on change?

Posted: Tue Sep 02, 2014 7:40 am
by namita
What is the source of this question?

Re: Question on change?

Posted: Tue Sep 02, 2014 10:37 am
by nagarwal
passionate pmp free questions

Re: Question on change?

Posted: Sat Sep 06, 2014 4:47 am
by taterarpit
what is the correct answer?

Re: Question on change?

Posted: Sat Sep 06, 2014 5:21 am
by saket
Its not necessary to match your thought process with each mock test, finally the PMI is the one who is gona take final call , each writer (including me :-) ) may have some different view for things

The deliverables as well as the schedule baselines of your project have been changed three times. Which of the following is MOST LIKELY the cause of the changes?


Change in deliverable mean unstable scope, which in turn resulting in change of schedule, since it is getting baseline which shows PM and team is doing replanning and sponsor is approving the replanning again and again.

Now look for options
1. The lack of clear instructions from project sponsor.
 
Could be the reason that is why he is ok for replanning.

2. Incomplete project management plans.

I am not getting any clue where it shows that project management plan was incomplete and that is resulting in change, rather question is saying we have baselines

3. The lack of a signed-off project charter.


No reason to believe this

4. Incomplete project scope management plans


This could be the reason since the change is happening in scope , but since we have approval of baseline i prefer selective option 1.