What is Schedule Variance (SV) ?

Postby saket Thu Aug 28, 2014 10:53 am

Schedule Variance (SV)

PMBOK Guide Page 224 defines it as
The amount by which the project is ahead or behind the planned delivery date, at a given point in time, expressed as the difference between the earned value and the planned value.


Practice Standard for Earned Value Management (by PMI) defines it as

The schedule variance (SV) determines whether a project is ahead of or behind schedule in accomplishing work.


It further says...

Schedule variance (SV) is very often misinterpreted as a time based indicator , for example are we early or late? it is not, rather its an indication of the physical status


Which one do you think is more accurate ?
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: What is Schedule Variance (SV) ?

Postby umeshbww Fri Aug 29, 2014 6:51 pm

Saket - I think PMBOK describes it very well.

Becoz PMBOK is document for passing PMP Exam :)
GOAL : PMP Certified by 24th Sept 2014 -- ACCOMPLISHED
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: What is Schedule Variance (SV) ?

Postby saket Sat Aug 30, 2014 12:35 am

:D :D :D :D :D i will discuss this in today's web session.... we will also try our best to record the session but since its huge , it may take sometime to be live on youtube....
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: Bing [Bot] and 10 guests