Page 1 of 1

Scope Management

Posted: Wed Aug 27, 2014 5:53 pm
by taterarpit
Tom is the project manager of an accounting project. He has just finished defining the scope for the project
and is creating the WBS. He goes to his organizational process asset library and finds a WBS from a past project
to use as a jumping off point. Which of the following is the tool of the Create WBS process is he using?

A.Decomposition
B. Delphi Technique
C. Brainstorming
D. Templates

Re: Scope Management

Posted: Wed Aug 27, 2014 6:24 pm
by signor_rk
Possible Option is Option # D Template , but since Template is not a tool , rather it is an OPA , then the next possible Option is # A Decomposition.

Re: Scope Management

Posted: Wed Aug 27, 2014 11:55 pm
by umeshbww
D. Templates is not at all possible option because template is Input not tool.
He goes to his organizational process asset library and finds a WBS from a past project
to use as a jumping off point.
This statement Only serve purpose of confusing.

Create WBS process only has only 2 tools : Decomposition and Expert Judgement

Re: Scope Management

Posted: Thu Aug 28, 2014 3:38 am
by taterarpit
yes...this is what i was thinking as mentioned by Umesh but answer they have given is Templates which is very confusing ....