Postby taterarpit Wed Aug 27, 2014 5:53 pm

Tom is the project manager of an accounting project. He has just finished defining the scope for the project
and is creating the WBS. He goes to his organizational process asset library and finds a WBS from a past project
to use as a jumping off point. Which of the following is the tool of the Create WBS process is he using?

A.Decomposition
B. Delphi Technique
C. Brainstorming
D. Templates
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Scope Management

Postby signor_rk Wed Aug 27, 2014 6:24 pm

Possible Option is Option # D Template , but since Template is not a tool , rather it is an OPA , then the next possible Option is # A Decomposition.
Regards ,

Ranjit
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: Scope Management

Postby umeshbww Wed Aug 27, 2014 11:55 pm

D. Templates is not at all possible option because template is Input not tool.
He goes to his organizational process asset library and finds a WBS from a past project
to use as a jumping off point.
This statement Only serve purpose of confusing.

Create WBS process only has only 2 tools : Decomposition and Expert Judgement
GOAL : PMP Certified by 24th Sept 2014 -- ACCOMPLISHED
taterarpit
Contributor
Contributor
Posts: 111
Joined: Sat Jul 26, 2014 6:42 pm

Re: Scope Management

Postby taterarpit Thu Aug 28, 2014 3:38 am

yes...this is what i was thinking as mentioned by Umesh but answer they have given is Templates which is very confusing ....