Now, i have one more questions ( rather confusion i should say )...As we know that the purpose of Validate Scope is verifying deliverable and WPD data gives us RAW data which needs to be refined in order to make it ready for verification. So can we verify any information coming in form of WPD or first that information should go for Quality control check and then that particualr deliverable should be ready for validation. Please let me know if this sounds confusing, i will try to rephrase the question. Thanks!!

Re: Validate Scope

Posted: Wed Aug 27, 2014 4:31 pm
by saket
Lets look at PMBOK definition of validate scope

PMBOK Page 105
Validate Scopeā€”The process of formalizing acceptance of the completed project deliverables.


WPD data verification is not the goal of validate scope, and it also not about verifying the deliverable... it is about validating the deliverables , we had long discussion on this in our clarification session , since you also have access to exclusive forum, you may check this link viewtopic.php?f=12&t=762

This process does not work on WPD refinement , this process usages it to know what has been done on deliverable which has come for validation... this is how PMBOK defines the use of WPD in this process

5.5.1.5 Work Performance Data
Described in Section 4.3.3.2. Work performance data can include the degree of compliance with requirements,
number of nonconformities, severity of the nonconformities, or the number of validation cycles performed in a
period of time.