Question on Project Closure:

Postby Piyali Tue Aug 26, 2014 12:17 pm

"You have completed your project and performing project closure activities. What should you do LAST in this process?"

A Creating final product, service, or result transition

B Releasing project resources working on the project

C Updating organizational process assets

D Accepting deliverables
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: Question on Project Closure:

Postby umeshbww Tue Aug 26, 2014 4:22 pm

Question mentioned Last thing in Closing Phase. PMBOK pg 58
You follow sequences in Closing phase in this order. D -> A -> C -> B

Right answer is B. Releasing project resources working on the project

Note : D. Accepting deliverables is output of Monitor and Control process group