I was reading PMBOK and just noticed a point which says " following activities may occur during project closure " and one of the items listed is as follows ...

" Perform team member's assessments and release project resources ".

I do understand about release of resources but team member's performance assessment happens in closure or during develop project team which is part of execution. Just got confused here.

Source :- Page 58 PMBOK 5th Edition.

Re: Project Management Process

Posted: Tue Aug 26, 2014 5:53 am
by signor_rk
What I understand so far is :
In Develop Project Team process , assessment for performance is done for the overall project team , whereas , in the Close Project or Phase process , it is done for individual Project Team members.

Re: Project Management Process

Posted: Tue Aug 26, 2014 6:38 am
by namita
Closure is the point where team will get dismantled... team members will go back to their functional departments. Before this happens, how team members performed in the current project under you as PM is something you should do formally. I recommend going through below webinar for more insights into close project/phase process