Control schedule

Postby prax Wed Aug 20, 2014 6:52 am

Hi, I have a doubt: The "control schedule" process, comes under: "monitoring and control". Now if "monitoring & control" generates "work performance reports" as output, then the output of "control schedule" should also be "work performance report". How should I remember this ?
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Control schedule

Postby saket Wed Aug 20, 2014 8:08 am

You may use our ITTO Excel sheet to visualize this, use filters... like filter output as "Work Performance Report" you will see only one process : Monitor and Control Project Work

and when you filer for Work Performance Information , you will see all KA control processes except Integration management

Validate Scope
Control Scope
Control Schedule
Control Costs
Perform Quality Control
Control Communications
Monitor and Control Risks
Control Procurements
Control Stakeholder Engagement

You can get ITTO sheet from here : http://www.izenbridge.com/pmp/resources/
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Control schedule

Postby signor_rk Wed Aug 20, 2014 10:54 am

On the other hand , the new terms as per PMBOK5 for the following processes are :
Perform Quality Control (OLD) ...... Control Quality (NEW)
Monitor and Control Risks (OLD) ..... Control Risk (NEW)
This should be okey ...
Regards ,

Ranjit
prax
Posts: 2
Joined: Fri Aug 08, 2014 4:00 am

Re: Control schedule

Postby prax Thu Aug 21, 2014 3:21 am

Thanks for the ITTO sheet, but I saw in the sheet that:

1) For say Integration -> Monitor & Control -> Work performance Information is an Input -> Work performance report is an output
Also for Integration -> Change control -> Work performance report is an Input

2) but for, Time mgmt -> Control Schedule -> Work performance data is an input -> Work performance information is output

Why the difference please ?
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Control schedule

Postby signor_rk Thu Aug 21, 2014 5:59 am

I also downloaded the ITTO excel file. This is quite handy indeed. Thanks Saket for that.
Regards ,

Ranjit
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Control schedule

Postby saket Thu Aug 21, 2014 6:28 am

have a look at this video... if not done already... and we can discuss this in this week clarification session if needed.

Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF