Which of the following tools is used to document the lessons that were learned when the
contract was administered?
A. Quality audit
B. Buyer-conducted performance review
C. Contract review
D. Procurement audit

Headfirst-D
Discussion- "Performance Review" is a T&T of Administer/Control Procurment. so shouldn't B be answer? Why PM has to wait till the Procurment closure when final Audit is conducted to document LL which were identified earlier??

--Sud
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Control/Close Procurement-LL

Postby namita Thu Aug 14, 2014 7:52 am

when the question is on formal processes or t&t we need to go to best solution.

If this would not have been related to procurement, we may document LL at any point but in case of procurement, outside party is involved. We can't really do lessons learnt as an when we want. Parties involved are not there for that. while procurement Audit we may refer perf review inputs to formally document LL