Mike is a project manager for an IT technology implementation project. He is using an Ishikawa
diagram to figure out what could cause potential risks on his project. Which process is he doing?
A. Identify Risks
B. Perform Qualitative Risk Analysis
C. Control Quality
D. Plan Risk Responses

Headfirst-A

Discussion-Ishikawa diag is used in Control Qlty (7BQT) as well as Identify Risks(Diag Tech). How to determine answer?
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Ishikawa

Postby signor_rk Thu Aug 14, 2014 5:14 am

"what could cause potential risks on his project" , that means Mike is still in Planning and in the IDENTIFY RISK Process.
But if the sentence started like this " what could have caused / what could have been the potential risks on his project" , then it will direct to Control Quality Process.
Hope I am Okey. Forum Co-ordinators/Moderators , please suggest us.
Thanks
Regards ,

Ranjit
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Ishikawa

Postby namita Thu Aug 14, 2014 10:25 am

Agree with rk...