Postby Sud Wed Aug 06, 2014 8:27 pm

You are in the 10th month of a year long project and about to deliver the major product of your project. You have already received 75% of the total payment from the client. Your client is a non-governmental organization (NGO). You have just received a fax from the client saying that they are wrapping-up their operations from the region because of a change in the government. The new government has decided to close down this NGO because of fraud allegations. You are shocked to receive this news and call your boss to get a confirmation from him. He has also received the same news from other sources and asks you to terminate the project and release the team. What must you do?

A. Update lessons learned, release payments of your suppliers, pay all the employees and relieve them from their duties.

B. Release payments of your suppliers, pay all the employees and relieve them from their duties.

C. Close all project documents, release payments of your suppliers, pay all the employees and relieve them from their duties.

D. Release payments, check the termination clause in contract, and relieve employees from their duties.

Scordo. Discussion- What should be the correct sequence? Should not it be A?

--Sud
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Question for Discussion-Closure

Postby namita Thu Aug 07, 2014 5:11 am

Hi Sud,

Can I request you to go through the below webinar? there was one earlier question as well where closing was confusion. This will help you
https://www.youtube.com/watch?v=CJongXKL91A
manishpn
Expert
Expert
Posts: 2474
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question for Discussion-Closure

Postby manishpn Sun Dec 10, 2017 8:29 pm

would go with option D since it involves contract and you have received news from client to wind up project,
option D is the only one that mentions termination clause in the contract
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist