Perform Quality Assurance

Posted: Sun Aug 03, 2014 8:36 am
by taterarpit
Why quality control measurement is an input for Perform Quality Assurance , instead it should be used in Control Qullity? please sugges

Re: Perform Quality Assurance

Posted: Mon Aug 04, 2014 10:19 am
by namita
Control quality measurements are output of control quality process (Control Quality is the process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes)

Now first thing you need to understand is monitoring and control happens during/in parallel to planning & execution. Refer page 47 of PMBOK. So output of controlling can go to executing process

Now Quality assurance is the process of auditing the quality requirements and the results from quality control measurements to ensure that appropriate quality standards and operational deļ¬nitions are used.
from definition only its clear that QA needs control quality measurement as input to audit and come up with right quality processes

Re: Perform Quality Assurance

Posted: Mon Aug 04, 2014 11:52 am
by sunku65
This Process is iterative, when deliverable needs to be rework(Rejected one) that time need this Quality Control Measurements to self check by the team member or by Audit Team.

Re: Perform Quality Assurance

Posted: Mon Aug 04, 2014 12:14 pm
by namita
Agree Sunku65

Re: Perform Quality Assurance

Posted: Sat Aug 09, 2014 7:25 pm
by taterarpit
Thanks :-)